Track record at a glance
Deyaar has 5 projects in the Dubai Land Department register this year. None is past its handover date today. Owners who sold a finished Deyaar home since 2025 made a median 28% (7% sold for less than they paid).
Timeline
Every Deyaar tower we cover, by the year it was finished or is due. 1 completed, 0 off-plan.
1 more towers have no year in our record.
Year: handover year in our building record. Select a square to open the tower.
On the map
1 of 2 Deyaar towers placed on the map of Dubai. Black: completed. Yellow: off-plan. Bigger dot: more sales in 12 months.
Position: our building record. Select a dot to open the tower. Every tower on the 3D map.
The RealEstateRanking for October 2026: developers
Deyaar is #7 of 47 in the developer league for October 2026, score 72.0 out of 100 across 17 metrics.
Awards, October 2026: Safest Off-plan
| Group | Metric | Deyaar | Rank |
|---|---|---|---|
| Scale | Sales, 12 months | 690 | #21 of 126 |
| Scale | Sales value, 12 months | AED 1.5bn | #20 of 125 |
| Scale | Towers | 28 | #21 of 126 |
| Scale | Off-plan towers (pipeline) | 3 | #68 of 126 |
| Price | Median AED per sq ft | AED 1,351 | #74 of 100 |
| Market | Gross rental yield | 6.5% | #38 of 99 |
| Market | Months of supply for sale | 6.9 | #49 of 91 |
| Delivery | On time (2026 register) | 100% | #1 of 33 |
| Delivery | Homes past handover date | 0 | #1 of 33 |
| Delivery | Median months late (late projects) | 0.0 | #1 of 33 |
| Delivery | Handover dates pushed back since July | 0% | #1 of 33 |
| Delivery | Finished late in 2026 | 67% | #8 of 13 |
| Resale | Owner gain on resale, finished homes | +28% | #10 of 29 |
| Resale | Owner return a year, finished homes | 10.1% | #15 of 29 |
| Resale | Finished homes resold below price paid | 7% | #11 of 29 |
| Resale | Off-plan resales at or below price paid, 2026 | 7% | #1 of 9 |
| Transparency | Projects with a named main contractor | 60% | #12 of 33 |
See the full developer league, the sales league and the awards →
Pool: 126 developers with 5+ towers. Rank 1 = best on that metric (for delays and resales below the price paid, lowest is best). Method on the league page.
Handover: on time or late
No Deyaar project in this year's DLD register is past its handover date today.
Finished in 2026: 3 projects, 2 more than a month after the due date in the register.
Why the official record looks on time: when a project finishes, the register replaces the due date with the finish date, and a due date that is pushed back replaces the old one. Late handovers only show if the register is read over time. BUY DUBAI keeps a copy each time it reads it. Across Dubai, off-plan homes in late projects resold for a median +1.4% in 2026, against +15.5% in projects on time; 48% resold at or below the price paid, against 20%.
What owners made
Finished Deyaar homes resold since January 2025: median gain 28% over a median 2.3 years, about 10.1% a year. 7% sold below the price paid. Dubai: 23% median, 12% below paid.
Off-plan Deyaar homes resold before handover in 2026: median +21.6%; 7% went at or below the price paid (5% below). Dubai: 45% at or below.
162 resales: the same home sold twice, 30 days or more apart, in the DLD record. Gain = second price against first, before fees.
Who builds
Main contractor named for 3 of 5 Deyaar projects in the register. Most used: Naresco Contracting (1); Gulf Asia Contracting (1); NEW SYSTEM ENGINEERING (1).
| Project | Main contractor | Source |
|---|---|---|
| MAR CASA | Naresco Contracting | source |
| Regalia | Gulf Asia Contracting | source |
| TALIA RESIDENCES | NEW SYSTEM ENGINEERING | source |
Found 20 October 2026 from public pages (developer and contractor sites, press, Propsearch, social posts) and read by machine; check before you rely on it. A change of main contractor during construction is one of the earliest signs of a late handover.
Questions
- Does Deyaar hand over on time?
- None of its 5 projects in the 2026 DLD register is past its handover date today. Checked 20 October 2026.
- Do Deyaar homes hold their value?
- Finished homes resold since 2025 made a median 28% over 2.3 years; 7% sold for less than the owner paid. Dubai median: 23%.
- Who builds Deyaar projects?
- Named main contractors: Naresco Contracting (1); Gulf Asia Contracting (1); NEW SYSTEM ENGINEERING (1). Found for 3 of 5 projects in the 2026 DLD register.
Every Deyaar tower we cover
2 towers in Business Bay (1) and Dubai Silicon Oasis (1): 2 completed, 0 off-plan. Select a column heading to sort.
| Tower | Community | Status | Tower type | Price band | AED per sq ft, 12 months | Sales, 12 months | For sale now |
|---|---|---|---|---|---|---|---|
| The Burlington | Business Bay | Completed 2013 | Mixed-use tower | – | – | – | – |
| Ruby Residence | Dubai Silicon Oasis | Completed | Residential tower | Upper mid-range | 958 | 9 | – |
More
Sources
- Track record at a glance — Checked 20 October 2026. Register: Dubai Land Department project data (projects with a start or end date in 2026). Sales: DLD unit sale records in BUY DUBAI.
- Table: Every Deyaar tower we cover — Source: Dubai Land Department sale records, as built into BUY DUBAI. The developer is the one in our building record. AED per sq ft = median of unit sales in the last 12 months.