BUY DUBAI / Market intelligence

Is my Dubai off-plan project late? Handover tracker, calendar and delays

Check any project's handover date, how late it is and the developer's record. Homes handed over each month, what is due near you, and which developers are behind.

DLD project data to 6 November 2026

3,730homes handed over, October 2026 (Dubai, DLD)
36,295homes due in the next 90 days (Dubai, DLD end date)
46,692homes in 169 overdue projects, median 4.2 months late
38end dates moved later since 15 June 2026

Is my project on time? Check a project

Type a project, developer or area. You get the official end date, how far it is built, how late it is, what the developer's other projects are doing, and what to do next.

Try: AZIZI VENICE 14 · Binghatti Developers · Madinat Al Mataar. 2,068 projects: Dubai from the DLD register and daily feed, other emirates from developer dates.

How many new homes land each month

Dubai handed over 51,661 homes in the last 12 full months. Register end dates put 163,173 homes in the next 18 months, peaking in December 2026, plus 46,692 overdue homes that could arrive any time. More homes handed over in an area means more units competing for tenants and resale buyers there.

020,00040,00060,00080,000Nov 24: 869 homes handed overDec 24: 4,186 homes handed overJan 25: 633 homes handed overFeb 25: 1,267 homes handed overMar 25: 1,767 homes handed overApr 25: 996 homes handed overMay 25: 314 homes handed overJun 25: 278 homes handed overJul 25: 753 homes handed overAug 25: 614 homes handed overSep 25: 4,539 homes handed overOct 25: 2,701 homes handed overNov 25: 13,409 homes handed overDec 25: 2,548 homes handed overJan 26: 870 homes handed overFeb 26: 299 homes handed overMar 26: 1,213 homes handed overApr 26: 5,142 homes handed overMay 26: 4,411 homes handed overJun 26: 4,792 homes handed overJul 26: 6,903 homes handed overAug 26: 3,109 homes handed overSep 26: 5,235 homes handed overOct 26: 3,730 homes handed overoverdue: 46,692 homes overdue now, not finishedNov 26: 1,862 homes due (register end date)Dec 26: 35,844 homes due (register end date)Jan 27: 2,524 homes due (register end date)Feb 27: 3,035 homes due (register end date)Mar 27: 13,216 homes due (register end date)Apr 27: 6,189 homes due (register end date)May 27: 5,837 homes due (register end date)Jun 27: 12,925 homes due (register end date)Jul 27: 3,609 homes due (register end date)Aug 27: 8,005 homes due (register end date)Sep 27: 8,938 homes due (register end date)Oct 27: 6,059 homes due (register end date)Nov 27: 6,443 homes due (register end date)Dec 27: 26,741 homes due (register end date)Jan 28: 3,492 homes due (register end date)Feb 28: 3,306 homes due (register end date)Mar 28: 11,798 homes due (register end date)Apr 28: 3,350 homes due (register end date)todayNov 24Feb 25May 25Aug 25Nov 25Feb 26May 26Aug 26overdueJan 27Apr 27Jul 27Oct 27Jan 28Apr 28
Dubai homes per month: handed over (last 24 months), overdue now, and due by register end date (next 18 months)
handed over (DLD completion date)overdue nowdue by register end date

New homes in your area

Pick a DLD area to see what was handed over there in the last 12 months, what is overdue, and what is due next.

Which developers are behind

Homes in unfinished Dubai projects in the daily DLD feed, for the 12 developers with the most. Red is past the register end date; orange would finish more than six months late at its pace so far; purple had its end date moved.

010,00020,00030,00040,000Binghatti DevelopersBinghatti Developers: 10,116 homes on scheduleBinghatti Developers: 4,501 homes projected late >6mBinghatti Developers: 11,639 homes overdue26,256 homes · 44% overdueEmaar DevelopmentEmaar Development: 9,979 homes projected late >6m9,979 homes · 0% overdueAzizi DevelopmentsAzizi Developments: 420 homes on scheduleAzizi Developments: 336 homes date movedAzizi Developments: 6,500 homes overdue7,256 homes · 90% overdueAl Habtoor City Real Estate DevelopmAl Habtoor City Real Estate Development: 6,717 homes on schedule6,717 homes · 0% overdueThe Palm - JumeirahThe Palm - Jumeirah: 3,216 homes projected late >6m3,216 homes · 0% overdueDanube Properties DevelopmentDanube Properties Development: 2,238 homes overdue2,238 homes · 100% overduePrime Marina Property DevelopersPrime Marina Property Developers: 1,264 homes overdue1,264 homes · 100% overdueHRE Real Estate DevelopmentHRE Real Estate Development: 1,123 homes overdue1,123 homes · 100% overdueObj1 Real Estate DevelopmentObj1 Real Estate Development: 142 homes on scheduleObj1 Real Estate Development: 340 homes projected late >6mObj1 Real Estate Development: 587 homes overdue1,069 homes · 55% overdueImtiaz Real Estate Investment & DeveImtiaz Real Estate Investment & Development: 361 homes on scheduleImtiaz Real Estate Investment & Development: 260 homes projected late >6mImtiaz Real Estate Investment & Development: 442 homes overdue1,063 homes · 42% overdueDawn Real Estate DevelopmentDawn Real Estate Development: 955 homes overdue955 homes · 100% overdueReportage Prime PropertiesReportage Prime Properties: 653 homes projected late >6mReportage Prime Properties: 239 homes overdue892 homes · 27% overdue
Unfinished homes by developer and status (Dubai, DLD daily feed)
on scheduleprojected late >6mdate movedoverdue

Where the handovers are

1,082 projects due in the next 18 months or overdue. Click a point, then "Check this project". Points marked approximate sit at the centre of their DLD area.

overdueprojected late >6mdate movedon scheduledeveloper datepast developer date

Pace check: when will it really be ready?

For any off-plan building. Take the construction start and per cent built from the developer's progress report or the Dubai REST app.

What the numbers say

The Dubai Land Department project register marks 8 projects with 3,730 homes as finished in October 2026. Over the last 12 full months the total is 61 projects and 51,661 homes.

84 Dubai projects with 36,295 homes have a register end date in the next 90 days. 169 projects with 46,692 homes are already past their end date and not finished; the median is 4.2 months late.

Since 15 June 2026 the register moved the end date of 39 projects; 38 moved later, by a median of 5.9 months. On its building pace so far, the median unfinished project would finish 23.3 months after its end date. Read that as an upper bound: building runs slow early.

Outside Dubai no completion register is published that we hold. The calendar uses the handover date each developer gives on Property Finder for Abu Dhabi, Sharjah, Ajman, Ras Al Khaimah and Umm Al Quwain.

In 30 news, video or podcast mentions, the handover date people quote is three or more months later than the register end date.

Questions and answers

How many homes were handed over in Dubai last month?

3,730 homes in 8 projects in October 2026, by the completion dates in the DLD project register.

How many off-plan projects in Dubai are late?

169 projects with 46,692 homes are past the register end date and not finished, as of 6 November 2026.

How do I check if my off-plan project is late?

Type the project, developer or area into "Check a project" at the top of this page. It shows the register end date, per cent built, months late, the developer's record and news mentions. Confirm with the developer and the Dubai REST app (DLD).

Does a late register date mean a late handover to me?

Not always. The register shows the developer's current end date; your sale agreement can set a different date. Ask the developer for the completion certificate date and the handover notice in writing.

Where do handover dates for Abu Dhabi, Sharjah and RAK come from?

From the developer's own handover date on Property Finder. These are not official and are not checked against a regulator.

Full lists

Every number above, row by row. Open a list.

Overdue projects (169)

Not finished and past the register end date, largest first.

ProjectDeveloperDLD areaHomesRegister end dateMonths lateBuiltProjected finish
AZIZI VENICE 14Azizi DevelopmentsMadinat Al Mataar3,43830 May 20265.3——
AZIZI VENICE 7Azizi DevelopmentsMadinat Al Mataar2,35828 January 20269.3——
Binghatti HillviewsBinghatti DevelopersAl Barshaa South Second2,3391 April 20267.233%24 February 2031
Binghatti EliteBinghatti DevelopersMe'Aisem First1,74530 June 20264.253%10 July 2028
Binghatti AquariseBinghatti DevelopersBusiness Bay1,60231 October 20260.221%20 December 2032
Residences Du Port, Dubai Marina, Autograph Collection ResidencesPrime Marina Property DevelopersMarsa Dubai1,2646 June 20265.071%29 May 2027
Binghatti AmberhallBinghatti DevelopersAl Barsha South Fourth1,15728 February 20268.270%27 July 2027
Sportz By DanubeDanube Properties DevelopmentAl Hebiah Fourth1,11030 March 20267.3——
LIVING LEGENDS PHASE 6Dawn Real Estate DevelopmentWadi Al Safa 395516 July 20263.7——
One by BinghattiBinghatti DevelopersBusiness Bay78330 May 20265.350%26 June 2029
LIME LIGHT TWIN TOWERSLime Light Real Estate DevelopmentAl Hebiah Fourth73430 June 20264.2——
Binghatti SkyhallBinghatti DevelopersBusiness Bay72831 August 20262.231%15 September 2030
KYOTO BY ORO24Oro24 Real Estate DevelopmentAl Barshaa South Third70820 September 20261.517%—
BEACH OASIS 2Azizi DevelopmentsAl Hebiah Second70430 April 20266.2——
Burj Binghatti Jacob & Co. ResidencesBinghatti DevelopersBusiness Bay67130 June 20264.252%8 August 2030
Binghatti RubyBinghatti DevelopersAl Barsha South Fourth62828 February 20268.265%28 October 2027
MAR CASADeyaar Development (P.J.S.C)Madinat Dubai Almelaheyah58531 October 20260.267%3 June 2028
Aveline Residences by Citi DevelopersCiti Developers Real Estate DevelopmentAl Barsha South Fourth56826 July 20263.442%30 July 2030
Viewz 1 By DanubeDanube Properties DevelopmentAl Thanyah Fifth56430 June 20264.266%9 July 2028
Viewz 2 By DanubeDanube Properties DevelopmentAl Thanyah Fifth56430 June 20264.265%19 August 2028
Skyhills III by HREHRE Real Estate DevelopmentAl Barsha South Fourth5631 June 20265.2——
Skyhills II by HREHRE Real Estate DevelopmentAl Barsha South Fourth5601 June 20265.296%8 December 2026
Binghatti StarlightBinghatti DevelopersAl Jadaf51131 March 20267.263%27 February 2028
Biltmore SufouhG J R E Real EstateAl Safouh First50129 January 20269.288%18 June 2027
Binghatti HavenBinghatti DevelopersAl Hebiah Fourth50131 March 20267.276%4 June 2027
Expo City ValleyExpo City Valley DevelopmentMadinat Al Mataar48631 January 20269.266%22 August 2028
Expo City Mangrove ResidencesExpo City Mangrove Residences DevelopmentMadinat Al Mataar47031 January 20269.291%3 March 2027
SAMANA SKYROSSamana Signature Real Estate DevelopmentsAl Barshaa South Third44130 April 20266.271%16 January 2028
The Orchard PlacePeak Summit Real Estate DevelopmentAl Barsha South Fourth41831 July 20263.243%19 March 2031
Binghatti HillsideBinghatti DevelopersAl Barshaa South Second41130 June 20264.280%11 April 2027
City Center ResidencesDAR Global PropertiesBurj Khalifa39730 September 20261.272%24 July 2028
NIKI LAUDA TOWERPLT PropertiesBusiness Bay38431 March 20267.20%—
UH WEST BY ELLINGTONEllington Properties DevelopmentAl Thanyah Fifth3813 March 20268.184%4 July 2027
UH EAST BY ELLINGTONEllington Properties DevelopmentAl Thanyah Fifth38130 March 20267.363%16 November 2028
AG SQUAREAG PropertiesWadi Al Safa 537230 September 20261.269%9 September 2028
Belle Reve By ZimayaZimaya PropertiesAl Barsha South Fourth36031 August 20262.280%4 June 2027
ROVE HOME RESIDENCES by IRTHIrth DevelopmentBurj Khalifa34930 April 20266.263%3 September 2028
THE FIFTH TOWERObject ONE Real Estate DevelopmentAl Barsha South Fourth34524 July 20263.450%4 June 2029
PIER 8Pier 8 Real Estate DevelopmentMarsa Dubai3418 March 20268.057%12 April 2030
Time 2Time PropertiesWadi Al Safa 53041 June 20265.287%28 May 2027
Bay Residences Dubai IslandsNakheel And Excelsior Real EstatePalm Deira30215 October 20260.748%3 December 2029
SAMANA MYKONOS SIGNATURESamana International Real Estate DevelopmentAl Barshaa South Third30030 April 20266.286%4 May 2027
PELaGOS By IGODigo Real Estate Development (Br OF Invest Group Overseas (L L C) )Marsa Dubai29631 March 20267.284%13 March 2027
Jouri HillsArada Developments L.L.C S.O.CMe'Aisem First29430 June 20264.278%24 September 2027
Violet TowerDubai Investment Real Estate (L L C)Al Barsha South Fourth28930 June 20264.290%26 February 2027
Binghatti MoonlightBinghatti DevelopersAl Jadaf28615 June 20264.719%4 May 2033
Binghatti TwilightBinghatti DevelopersAl Jadaf27730 April 20266.255%11 February 2028
MAG 777DNG Property DevelopmentAl Hebiah Fourth26615 January 20269.767%22 October 2027
Cove Edition Residence 2 By ImtiazImtiaz Real Estate Investment & DevelopmentWadi Al Safa 526015 October 20260.760%13 March 2028
Verdana Residence 2Reportage Prime PropertiesDubai Investment Park First23930 April 20266.220%6 March 2035
Keturah ResortMAG OF Life FZAl Jadaf23526 February 20268.316%—
Nad Al Sheba Gardens Phase 3Al Qudra EstatesNad Al Shiba First23519 April 20266.697%14 December 2026
WAREF residences by sido developmentSido DevelopmentAl Barsha South Fourth2281 May 20266.281%18 June 2027
MIAMI BY SDSamana SI Holding Limited Dubai BranchAl Barsha South Fifth22031 July 20263.271%24 April 2028
EVERGRIN HOUSEObj1 Real Estate DevelopmentAl Satwa21930 June 20264.255%18 June 2028
Samana WavesSamana SI Holding Limited Dubai BranchAl Barsha South Fourth21715 April 20266.791%15 April 2027
Central Park PlazaCitywalk Residential 1Al Wasl2128 October 20261.044%30 July 2030
Terrazzo ResidencesTaraf DevelopmentAl Barsha South Fourth21120 May 20265.6——
Weybridge Gardens 3Leos DevelopmentWadi Al Safa 520820 August 20262.624%14 October 2032
Luminar Tower 1Obj1 Real Estate DevelopmentAl Barsha South Fifth20015 October 20260.740%6 February 2030

Overdue homes by developer

DeveloperProjectsHomes
Binghatti Developers1311,639
Azizi Developments36,500
Danube Properties Development32,238
Prime Marina Property Developers11,264
HRE Real Estate Development21,123
Dawn Real Estate Development1955
Ellington Properties Development5822
Lime Light Real Estate Development1734
Oro24 Real Estate Development1708
Samana SI Holding Limited Dubai Branch3610
Obj1 Real Estate Development3587
Deyaar Development (P.J.S.C)1585
Citi Developers Real Estate Development1568
G J R E Real Estate1501
Samana International Real Estate Development2498
Dubai projects due in the next six months (85)
Register end dateProjectDeveloperDLD areaHomesBuiltStatus
21 November 2026MAS Barsha ResidencyM A S Real Estate DevelopmentAl Barsha First24226%projected late >6m
25 November 2026ELARAJumeirah Hills DevelopmentUm Suqaim Third24064%projected late >6m
25 November 2026THE VYNE RESIDENCESMetrical Real Estate DevelopmentAl Barsha South Fifth26380%projected late >6m
30 November 2026DAMAC HILLS - GEMS ESTATES 1Damac Crescent PropertiesAl Hebiah Third0—date moved
30 November 2026SeascapeMina Rashid PropertiesMadinat Dubai Almelaheyah39579%projected late >6m
30 November 2026Mallside ResidenceRoyal Dunes Real Estate DevelopmentHadaeq Sheikh Mohammed Bin Rashid14883%on schedule
30 November 2026SEA LEGEND ONE BY MVS REAL ESTATEM V S Real Estate DevelopmentPalm Deira6522%projected late >6m
30 November 2026VIVID TOWERObj1 Real Estate DevelopmentAl Barsha South Fifth14712%projected late >6m
1 December 2026Trinity By KarmaKarma Realty DevelopersAl Barshaa South Third30931%projected late >6m
1 December 2026One BeverlyH M B Homes Real Estate DevelopmentAl Barshaa South Third38973%projected late >6m
14 December 2026THE EIGHTY THREEOksa DeveloperMadinat Al Mataar7060%projected late >6m
15 December 2026Sapphire 32 by Dar AlkaramaDAR Al Karama Real EstateAl Barsha South Fourth23262%projected late >6m
15 December 2026Luxur Tower By ImtiazImtiaz Real Estate Investment & DevelopmentAl Barsha South Fourth36190%on schedule
15 December 2026Bhuvi ResidenceBravima Real Estate DevelopmentMadinat Al Mataar7032%projected late >6m
15 December 2026BLISS TOWERPure Bliss DevelopmentWadi Al Safa 513193%on schedule
15 December 2026Lusin Residences by Ermax DevelopmentErmax DevelopmentAl Warsan First5735%projected late >6m
15 December 2026TAVORA RESIDENCES BY JHK HEIGHTS REAL ESTATE DEVELOPMENTJHK Heights Real Estate DevelopmentWarsan Fourth9586%on schedule
20 December 2026Rose Mirage 1Icon Real Estate DevelopmentMadinat Al Mataar640%on schedule
24 December 2026Olivia ResidencesKarma Real Estate DevelopmentDubai Investment Park First23138%projected late >6m
25 December 2026The St. Regis Residences, Downtown DubaiEmaar DevelopmentBurj Khalifa9,48876%projected late >6m
25 December 2026Seaside by Prestige OnePrestige The Seaside Real Estate DevelopmentPalm Deira12153%projected late >6m
25 December 2026Eden HillsEden HillsHadaeq Sheikh Mohammed Bin Rashid2814%on schedule
25 December 2026Beach Walk Grand By ImtiazImtiaz BWG Real Estate DevelopmentPalm Deira11253%projected late >6m
25 December 2026Sunset Bay One By ImtiazImtiaz Sunset Real Estate DevelopmentPalm Deira6694%on schedule
25 December 2026Cove Edition Residence 3 By ImtiazImtiaz Real Estate Investment & DevelopmentWadi Al Safa 526044%projected late >6m
25 December 2026Zenith Tower J1Zenith Ventures Real Estate DevelopmentAl Barsha South Fourth7672%projected late >6m
26 December 2026LAYA COURTYARDLaya DevelopersAl Hebiah Second28951%projected late >6m
29 December 2026Baccarat Hotel and Residences, DubaiBC ResidencesBurj Khalifa9921%projected late >6m
30 December 2026LIV LUXMARINA LIV DEVELOPMENT (Br of MARINA 2 GROUP LIMITED ) - DUBAI BRANCHMarsa Dubai22987%on schedule
30 December 2026VAL BY KASCOKasco Real Estate DevelopmentAl Jadaf13473%projected late >6m
30 December 2026REEF 1000Reef Luxury DevelopmentWadi Al Safa 512667%projected late >6m
30 December 2026Beachfront Gates 1Dubai South Properties DWCMadinat Al Mataar7436%projected late >6m
30 December 2026Beachfront Gates 2Dubai South Properties DWCMadinat Al Mataar16242%projected late >6m
30 December 2026Al Haseen Residence 4Dugasta Properties DevelopmentSaih Shuaib 224812%projected late >6m
30 December 2026Cresswell ViewsADEV PROPERTIES (Br of ARADY PROPERTIES - PSC )(Dubai Branch )Madinat Al Mataar5660%projected late >6m
30 December 2026Unique OneZenith Luxury Real Estate DevelopmentMadinat Al Mataar430%on schedule
30 December 2026VERDANIA 3Obj1 Real Estate DevelopmentWadi Al Safa 51420%on schedule
30 December 2026EVERGRIN HOUSE 2Obj1 Real Estate DevelopmentAl Satwa19310%projected late >6m
30 December 2026Lucent Rise ResidencesNova Square Real Estate L.L.C S.O.CWarsan Fourth0—on schedule
31 December 2026TONINO LAMBORGHINI RESIDENCESGulf Land Property DevelopersNad Al Shiba First55360%projected late >6m
31 December 2026Address The BayEmaar DevelopmentMarsa Dubai49170%projected late >6m
31 December 2026Palm Beach Towers -1The Palm - JumeirahPalm Jumeirah1,07283%projected late >6m
31 December 2026MARINA SHORESEmaar Properties (P.J.S.C)Marsa Dubai44787%on schedule
31 December 2026Palm Beach Towers - 2The Palm - JumeirahPalm Jumeirah1,07282%projected late >6m
31 December 2026Palm Beach Towers -3The Palm - JumeirahPalm Jumeirah1,07274%projected late >6m
31 December 2026ORLA BY OMNIYATCrescent 17 Real Estate DevelopmentsPalm Jumeirah9070%projected late >6m
31 December 2026Mercedes-Benz Places | BinghattiBinghatti DevelopersBurj Khalifa16365%projected late >6m
31 December 2026BiancaReportage Prime PropertiesWadi Al Safa 265356%projected late >6m
31 December 2026CANAL HEIGHTSVesta Real Estate DevelopmentBusiness Bay42636%projected late >6m
31 December 2026Fairway Villas 2Emaar Dubai South DWCMadinat Al Mataar176—on schedule
31 December 2026Al Habtoor TowerAl Habtoor City Real Estate DevelopmentBusiness Bay6,71790%on schedule
31 December 2026VITA GRANDE BY METEORAMeteora Real Estate DevelopmentAl Barsha South Fourth12164%projected late >6m
31 December 2026THE MELGRANOThe Melgrano Real Estate DevelopmentJumeirah Second1443%projected late >6m
31 December 2026Empire EstatesEmpire Real Estate DevelopmentsAl Barshaa South Third34560%projected late >6m
31 December 2026Royal Regency SuitesAlseeb Real Estate DevelopmentBusiness Bay24157%projected late >6m
31 December 2026Wadi Villas by AristaPBG Real Estate DevelopmentWadi Al Safa 33060%projected late >6m
31 December 2026Livel ResidenzaVantage Capital Real Estate DevelopmentAl Barsha South Fourth13720%projected late >6m
31 December 2026HILLMONT RESIDENCES BY ELLINGTONB L G DevelopmentAl Barsha South Fourth14526%projected late >6m
31 December 2026The PierContinental Investments LMDMadinat Dubai Almelaheyah28248%projected late >6m
31 December 2026La BoutiqueContinental Investments LMDAl Jadaf11952%projected late >6m
31 December 2026171 Garden HeightsJAD Global Real Estate DevelopmentAl Satwa15934%projected late >6m
31 December 2026Mira Villas designed by Bentley HomeM I R A DevelopmentsWadi Al Safa 336—on schedule
31 December 2026Ocean Pearl By SDSamana Star Real Estate DevelopmentPalm Deira10025%projected late >6m
31 December 2026LAZORD BY LAPISLapis PropertiesWadi Al Safa 331328%projected late >6m
31 December 2026HAVELOCK RESIDENCESAA And HMB Real Estate DevelopmentJabal Ali First23011%on schedule
31 December 2026Bonds Avenue ResidencesAmirah Living DeveloperPalm Deira757%on schedule
31 December 2026The Cube Quarter ResidencesAmwaj Alkhaleej Real Estate DevelopmentWadi Al Safa 35457%projected late >6m
31 December 2026Moonsa Residences 2Dugasta Properties DevelopmentWarsan Fourth1251%on schedule
31 December 2026Cresswell HomesAbdulwahed Faqeeh PropertiesMadinat Al Mataar7029%projected late >6m
31 December 2026The Haven IIMeraki Real Estate DevelopmentWadi Al Safa 322856%projected late >6m
31 December 2026Verano By PrescottPrescott Real Estate DevelopmentAl Hebiah Second26941%projected late >6m
31 December 2026Binghatti SkyriseBinghatti DevelopersBusiness Bay3,358—on schedule
31 December 2026GOLF TERRACESArgo Real Estate DevelopmentMe'Aisem First60—on schedule
31 December 2026Sunbliss Residences by Purvanchal Real Estate DevelopersPurvanchal Real Estate DevelopersJabal Ali First9932%projected late >6m
31 December 2026Reem by visionClear Vision Real Estate DevelopmentWadi Al Safa 220070%on schedule
31 December 2026Vio ResidencesModelux Real Estate DevelopmentWarsan Fourth876%on schedule
31 December 2026Soul by visionVision Platinum Real Estate DevelopmentMe'Aisem First17677%on schedule
31 December 2026Sukoon by NuriNuri Real Estate DevelopmentNad Al Shiba First4147%projected late >6m
31 December 2026NUMA RESERVEMirfa Serenity Real Estate DevelopmentWadi Al Safa 33510%projected late >6m
31 December 2026Greenfield LivingGreenfield Real Estate DevelopmentMadinat Al Mataar5233%projected late >6m
31 December 2026LATERAL ONEGrand Signature Real Estate DevelopmentWadi Al Safa 54079%on schedule
31 December 2026Binghatti HillcrestBinghatti DevelopersAl Barshaa South Third39660%projected late >6m
31 December 202618 Marlow RowSAI Avani Real Estate DevelopersAl Barsha South Fourth1852%projected late >6m
31 December 2026VUE DU LACMAG Palace Properties DevelopmentAl Thanyah Fifth06%on schedule
30 March 202724HCO&F Dhcc Real Estate DevelopmentUm Hurair Second9980%on schedule
Handover calendar: next 18 months, by emirate

Dubai: DLD register end date (homes shown); projects outside the daily DLD feed use the register as of 15 June 2026. Other emirates: developer handover date, not official.

MonthDubaiAbu DhabiSharjahAjmanRas Al KhaimahUmm Al Quwain
November 202611 1,862 homes··1··
December 202682 35,844 homes121257·
January 202713 2,524 homes11·5·
February 202721 3,035 homes12···
March 202762 13,216 homes21·3·
April 202726 6,189 homes···3·
May 202728 5,837 homes11···
June 202748 12,925 homes53·8·
July 202713 3,609 homes1····
August 202727 8,005 homes2····
September 202739 8,938 homes42···
October 202732 6,059 homes·····
November 202731 6,443 homes··2··
December 202784 26,741 homes16106143
January 202824 3,492 homes5749·
February 202818 3,306 homes·····
March 202852 11,798 homes2·13·
April 202821 3,350 homes12···
Recently completed projects
CompletedProjectDeveloperDLD areaHomesRegister end date
5 November 2026BEACH WALK RESIDENCES 3 BY IMTIAZImtiaz Real Estate Investment & DevelopmentPalm Deira8214 June 2026
28 October 2026Valores ResidencesValores Property DevelopmentJabal Ali First9031 August 2026
21 October 2026ALTAI TOWERTiger PropertiesAl Barsha South Fifth53831 January 2026
21 October 2026Solcasa ResidenceMatrix Real Estate DevelopmentNad Al Shiba First661 August 2026
9 October 2026Arabian Ranches lll - Anya 2Emaar DevelopmentWadi Al Safa 536230 December 2026
9 October 2026Arabian Ranches lll - AnyaEmaar DevelopmentWadi Al Safa 549231 October 2026
5 October 2026FernCitywalk Residential 1Al Wasl50921 March 2026
1 October 2026Binghatti GroveBinghatti DevelopersAl Barsha South Fourth1,06531 March 2026
1 October 2026LILIUM TOWERTiger PropertiesAl Barsha South Fifth60831 March 2026
23 September 2026Binghatti GhostBinghatti DevelopersAl Jadaf1,65431 March 2026
22 September 2026Beachgate by AddressEmaar DevelopmentMarsa Dubai64831 December 2026
21 September 2026Gharbi I ResidencesRabdan Real Estate DevelopmentAl Barshaa South Third35014 September 2026
21 September 2026Celia gardensAbou EID Real Estate DevelopmentNad Al Shiba First12315 May 2026
17 September 2026Mudon Al Ranim 8MDN Real EstateAl Hebiah Sixth22830 September 2026
17 September 2026Mudon Al Ranim 7MDN Real EstateAl Hebiah Sixth24830 September 2026
17 September 2026ELEGANCE TOWERPathfinder Property DevelopmentBurj Khalifa60428 February 2026
8 September 2026JomanaJumeirah Hills DevelopmentUm Suqaim Third77230 April 2026
3 September 2026ELBRUS TOWERTiger PropertiesAl Barsha South Fifth60831 March 2026
27 August 2026The EDGESelect Global DevelopmentBusiness Bay2,09411 October 2026
10 August 2026Beach Walk Residences 2Imtiaz GHD Real Estate DevelopmentPalm Deira13110 August 2026
6 August 2026Sobha Hartland Waves OpulenceSobhaAl Merkadh87130 September 2026
4 August 2026The Veranda Collection 2Pacifique Global PropertiesAl Barsha South Fourth137 April 2026
22 July 2026SPORTS VIEW RESIDENCE BY AL HELAL AL ZAHABYAl Helal Al Zahaby Real Estate DevelopmentWarsan Fourth2614 August 2026
21 July 2026Mohammed Bin Rashid Al Maktoum City, District 11- Opal GardensCrystal Three L.L.C-FzWadi Al Safa 343530 September 2026
16 July 2026LamaaJumeirah Hills DevelopmentUm Suqaim Third84027 January 2026
16 July 2026Skyhills I by HREHRE Real Estate DevelopmentAl Barshaa South Second2,3191 October 2026
16 July 2026Mudon Al Ranim 6MDN Real EstateAl Hebiah Sixth24230 July 2026
6 July 2026FH ResidencyForum Real Estate DevelopmentAl Barsha South Fifth66730 January 2026
1 July 2026ElviraDubai Hills EstateHadaeq Sheikh Mohammed Bin Rashid2,13931 December 2026
29 June 2026TULIP OASIS 10A M E Real Estate DevelopmentWadi Al Safa 330930 June 2026
25 June 2026Peninsula FourSelect Global DevelopmentBusiness Bay2,5611 February 2026
23 June 2026VYBGinco PropertiesBusiness Bay36328 February 2026
18 June 2026Golf HeightsEmaar Properties (P.J.S.C)Al Thanyah Third66831 December 2026
12 June 2026ErinCitywalk Residential 1Al Wasl46010 August 2026
7 June 2026Golf Residences by FortimoFortimo Real Estate DevelopmentHadaeq Sheikh Mohammed Bin Rashid43115 December 2026
19 May 2026BEACH WALK RESIDENCES 1Imtiaz Real Estate Investment & DevelopmentPalm Deira1641 June 2026
14 May 2026MAG 330MAG Property DevelopmentWadi Al Safa 41,3681 February 2026
11 May 2026ZaZEN IvyZazen Property DevelopmentJabal Ali First1961 February 2026
6 May 2026The Cove llThe Lagoons Phase ONEAl Khairan First2,68331 December 2026
26 April 2026Pearl House III by ImtiazImtiaz GHD Real Estate DevelopmentAl Barsha South Fourth3561 August 2026
Handovers by week and day

Last 12 weeks

Week startingProjectsHomes
2 November 2026182
26 October 2026190
19 October 20262604
5 October 202631,363
28 September 202621,673
21 September 202642,775
14 September 202631,080
7 September 20261772
31 August 20261608
24 August 202612,094
10 August 20261131
3 August 20262884

Last 30 days

DayProjectsHomes
5 November 2026182
28 October 2026190
21 October 20262604
9 October 20262854
End dates the register moved (39)
SeenProjectDeveloperOld end dateNew end dateMonths
5 November 2026AviorAcube Avior Real Estate Development15 September 20311 December 20312.5
30 October 2026Binghatti StarfallBinghatti Developers30 October 202730 September 202811.0
29 October 2026Expo Valley ViewsExpo City Valley Apartments30 June 202931 October 20294.0
26 October 2026ELYRA RESIDENCES BY ENAAMEnaam Properties Development30 September 202830 March 20295.9
26 October 2026ZetaAcube Zeta Real Estate Development15 September 203115 November 2028-34.0
26 October 2026VOLU BY ASAKAsak Real Estate Development31 December 202730 July 20287.0
9 October 2026Samana WavesSamana SI Holding Limited Dubai Branch5 November 202515 April 20265.3
9 October 2026AVA AT PALM JUMEIRAH BY OMNIYATAVA Residences Real Estate Developments31 December 202530 June 20265.9
9 October 2026MIAMI BY SDSamana SI Holding Limited Dubai Branch20 November 202531 July 20268.3
9 October 2026DAMAC HILLS - GEMS ESTATES 1Damac Crescent Properties15 September 202430 November 202626.5
9 October 2026Samana MykonosSamana International Real Estate Development30 June 202530 April 202610.0
9 October 2026VITA GRANDE BY METEORAMeteora Real Estate Development1 August 202531 December 202617.0
9 October 2026Olivia ResidencesKarma Real Estate Development30 March 202624 December 20268.8
9 October 2026PARKWOOD RESIDENCESArabian Gulf Properties30 October 202530 April 20266.0
9 October 2026Royal Regency SuitesAlseeb Real Estate Development31 December 202531 December 202612.0
9 October 2026POINT RESIDENCIAPacific Ventures31 December 202522 February 20261.7
9 October 2026Sea Mirror ResidencesLamar Development30 September 20265 December 202714.2
9 October 2026Cresswell HomesAbdulwahed Faqeeh Properties30 December 202631 December 20260.0
9 October 2026INTERSTELLAR TOWERBoujee Real Estate Development1 July 202830 September 20283.0
9 October 2026One By PrestonPreston Properties5 May 202731 December 20277.9
9 October 2026Almaara ResidencesHamara Home Real Estate Development30 May 202616 October 20264.6
9 October 2026KYOMI RESIDENCEAnax Developments1 February 20271 January 202811.0
9 October 2026Symphony by ChaimaaDeval Real Estate Development1 November 202631 August 202710.0
9 October 2026Lusin Residences by Ermax DevelopmentErmax Development26 April 202615 December 20267.7
9 October 2026Confident PrestonCasa Preston Real Estate1 July 202714 April 20289.5
9 October 2026AUM 99 ResidencesAUM 99 Home Real Estate Developments31 December 202831 March 20293.0
9 October 2026Elevia Residences IIValores Wbay Property Development31 July 202719 January 20285.7
9 October 2026Astra ResidencesDugasta Properties Development30 April 202731 August 20274.0
9 October 2026Orchid Residence 1Orchid Living Real Estate8 October 202531 March 20265.7
9 October 2026Azizi WaresAzizi Developments3 September 20274 March 20286.0
9 October 2026241 WatersideLegacy Star Real Estate Development28 February 202815 June 20283.5
9 October 2026Azizi DavidAzizi Developments16 September 202730 September 202812.5
9 October 2026Jasmine ResidenceDAR Comfort Real Estate31 October 202731 December 20272.0
9 October 2026Binghatti HillcrestBinghatti Developers1 October 202631 December 20263.0
9 October 2026Crystal TowerV H S Real Estate Developments1 December 20261 December 202824.0
9 October 2026Solaya (4,6)LA MER Central Property30 June 202930 September 20293.0
9 October 2026Solaya (5,7)LA MER Central Property30 June 202930 September 20293.0
9 October 2026Sky Line By Peace HomesPeace Homes Real Estate31 March 203030 May 20302.0
9 October 2026W1Malina W1 Real Estate Development4 December 202530 April 20264.8
Abu Dhabi, Sharjah, Ajman and RAK: developer handover dates
Developer dateProjectDeveloperEmirateCommunity
30 November 2026Azha Al Aamra ResidencesEmirates propertiesAjmanAl Amerah
1 December 2026The Source By AldarAldar PropertiesAbu DhabiSaadiyat Island
1 December 2026Sealine ResidenceAl Zorah DevelopmentAjmanAl Zorah
1 December 2026HayyanAlef GroupSharjahHayyan
1 December 2026Suroor Phase 2 By Alef GroupAlef GroupSharjahMuwaileh
1 December 2026Mayyas at The BayAdvanced PropertiesAbu DhabiYas Island
1 December 2026Sawa 1Alef GroupSharjahMuwaileh
1 December 2026Gateway Porto Al ZorahAl Zorah DevelopmentAjmanAl Zorah
1 December 2026RAK NB CollectionRAK PropertiesRas Al KhaimahMina Al Arab
1 December 2026Cape Hayat Phase 2 By RakRAK PropertiesRas Al KhaimahMina Al Arab
1 December 2026Al Alia TowerAl ThuriahSharjahAl Khan
1 December 2026PUD Residences 1Aldar PropertiesAbu DhabiAl Shamkha
1 December 2026Fortune Bay ResidencesTopero PropertiesRas Al KhaimahAl Marjan Island
1 December 2026Kabbali HillsArif DevelopmentsAjmanAl Helio
1 December 2026Sora Beach ResidencesAark DevelopersRas Al KhaimahAl Marjan Island
1 December 2026Ramhan IslandEagle HillsAbu DhabiRamhan Island
1 December 2026Joud TowerAlbatha DevelopmentSharjahAl Mamzar - Sharjah
1 December 2026GranadaBloom PropertiesAbu DhabiKhalifa City
1 December 2026The Icon TowerAdvanced PropertiesAbu DhabiYas Island
1 December 2026DeemAlef GroupSharjahHayyan
1 December 2026Al Naseem VillasModon PropertiesAbu DhabiAl Hudayriat Island
1 December 2026Ajman One Phase 2 By AqaarAqaar PropertiesAjmanAjman Downtown
1 December 2026Cape Hayat By RakRAK PropertiesRas Al KhaimahMina Al Arab
1 December 2026Bluebell ResidenceGJ Real EstateAjmanAl Amerah
1 December 2026Nawayef West HeightsModon PropertiesAbu DhabiAl Hudayriat Island
1 December 2026Ajwan ResidencesSharjah HoldingSharjahAjwan Residences
1 December 2026Reem Hills ApartmentsQ PropertiesAbu DhabiAl Reem Island
2 December 2026Selina Bay By ReportageReportage Real EstateAbu DhabiYas Island
30 December 2026Sawa phase 3 By Alef GroupAlef GroupSharjahMuwaileh
30 December 2026Porto PlayaEllingtonRas Al KhaimahMina Al Arab
30 December 2026Sawa phase 2 By Alef GroupAlef GroupSharjahMuwaileh
30 December 2026Suroor 4Alef GroupSharjahMuwaileh
30 December 2026Souq Al MamshaAlef GroupSharjahMuwaileh
30 December 2026Nourwatan ResidentialMaskan MS Contracting and Real EstateAbu DhabiAl Shamkha
30 December 2026Moonstone Residences Interiors by MissoniDurar GroupRas Al KhaimahAl Marjan Island
30 December 2026Sawa phase 4 By Alef GroupAlef GroupSharjahMuwaileh
31 December 2026Reeman Garden 1United Avenue Real Estate DevelopmentAbu DhabiAl Shamkha
1 January 2027Layla ResidencesEagle HillsSharjahAl Khan
1 January 2027The Unexpected Al Marjan Island Hotel & ResidencesAlmal Real Estate DevelopmentRas Al KhaimahAl Marjan Island
1 January 2027Sunshine BayThe Source of Fate Real Estate DevelopmentRas Al KhaimahAl Marjan Island
1 January 2027Waldorf Astoria ResidencesAl Hamra Real Estate Management ServicesRas Al KhaimahAl Hamra Village
1 January 2027Al Hamra WaterfrontAl Hamra Real Estate Management ServicesRas Al KhaimahAl Hamra Village
1 January 2027Ola ResidencesLacasa Living DevelopmentRas Al KhaimahAl Marjan Island
1 January 2027Seville at Bloom LivingBloom PropertiesAbu DhabiKhalifa City
1 February 2027Faradis TowerTiger PropertiesSharjahAl Mamzar - Sharjah
1 February 2027Fay Alreeman Phase 2 By AldarAldar PropertiesAbu DhabiAl Shamkha
28 February 2027Topaz ResidencesEagle HillsSharjahAl Khan
1 March 2027Manarat Living Phase 2 By AldarAldar PropertiesAbu DhabiSaadiyat Island
1 March 2027Ellington Views Phase 2 By Ellington PropertiesEllingtonRas Al KhaimahAl Hamra Village
1 March 2027The Ritz Carlton ResidencesRAK Hospitality HoldingRas Al KhaimahAl Wadi Desert
1 March 2027Ellington Views 1EllingtonRas Al KhaimahAl Hamra Village
31 March 2027Reeman Residence 01Towaiji Real Estate DevelopmentAbu DhabiAl Shamkha
31 March 2027Al Teneiji TowerAlteneiji DeveloperSharjahAl Mamzar - Sharjah
1 April 2027Park Beach Residence phase 2 By park GroupPark GroupRas Al KhaimahAl Marjan Island
1 April 2027Cala Del MarEllingtonRas Al KhaimahAl Marjan Island
1 April 2027Aqua ArcBNW DevelopmentsRas Al KhaimahAl Marjan Island
1 May 2027Anantara Sharjah ResidencesAradaSharjahAl Heerah
31 May 2027Perla Phase 3 By ReportageReportage Real EstateAbu DhabiYas Island
1 June 2027Madain SquareMada'in PropertiesSharjahAl Suyoh
1 June 2027AquinoBNW DevelopmentsRas Al KhaimahAl Marjan Island
1 June 2027La PerlaBNW DevelopmentsRas Al KhaimahAl Marjan Island
1 June 2027Manta Bay Phase 2Major DevelopersRas Al KhaimahAl Marjan Island
1 June 2027Ramhan Island Villas Phase 5Eagle Hills PropertiesAbu DhabiRamhan Island
1 June 2027John Richmond ResidencesMira DevelopmentsRas Al KhaimahRas Al Khaimah
1 June 2027Nesba Phase 3 By AradaAradaSharjahAljada
1 June 2027Reem Hills Phase 2 by Q PropertiesQ PropertiesAbu DhabiAl Reem Island
1 June 2027Quattro Del MarRAK PropertiesRas Al KhaimahMina Al Arab
1 June 2027Edge at Raha Island By RAKRAK PropertiesRas Al KhaimahMina Al Arab
1 June 2027Ramhan Island Villas Phase 6 By Eagle HillsEagle HillsAbu DhabiRamhan Island
1 June 2027Ramhan Island Villas Phase 7 By Eagle HillsEagle HillsAbu DhabiRamhan Island
1 June 2027Gardenia BayAldar PropertiesAbu DhabiYas Island
1 June 2027Al Danah Residential TowerDubai Investment PropertiesRas Al KhaimahAl Marjan Island
1 June 2027The Gate Phase 3 by AradaAradaSharjahAljada
1 June 2027Manta BayMajor DevelopersRas Al KhaimahAl Marjan Island
1 July 2027Sama Yas By Aldar PropertiesAldar PropertiesAbu DhabiYas Island
1 August 2027Radiant AtriumRadiant Enterprises Real EstateAbu DhabiAl Reem Island
18 August 2027The Source TerracesAldar PropertiesAbu DhabiSaadiyat Island
1 September 2027Ville 11BurtvilleAbu DhabiMasdar City
1 September 2027OlveraBloom PropertiesAbu DhabiKhalifa City
1 September 2027Safa 1 By AradaAradaSharjahAljada
1 September 2027Al SidrAldar PropertiesAbu DhabiSaadiyat Island
1 September 2027Carmona at Bloom LivingBloom PropertiesAbu DhabiKhalifa City
1 September 2027The Gate Phase 4 By AradaAradaSharjahAljada
30 November 2027Ajman Creek TowersGJ Real EstateAjmanAl Rashidiya
30 November 2027Al Aamra Tower 3GJ Real EstateAjmanAl Amerah
1 December 2027Al Ameera Village 5GJ Real EstateAjmanAl Ameera Village
1 December 2027The Art of TrioDurar GroupRas Al KhaimahAl Marjan Island
1 December 2027MeliaAradaSharjahTilal City
1 December 2027Barajeel TowersGJ Real EstateAjmanAl Rashidiya
1 December 2027JW Marriott ResidencesWOW ResortsRas Al KhaimahAl Marjan Island
1 December 2027AnberAradaSharjahAljada
1 December 2027Radiant Marina TowersRadiant Enterprises Real EstateAbu DhabiAl Reem Island
1 December 2027CoralAradaSharjahAl Ruwaidat Suburb
1 December 2027Arabian Hills EstateDeca Real Estate DevelopmentsAbu DhabiAl Faqa'a
1 December 2027Ramhan Island Villas Phase 3 By Eagle HillsEagle Hills PropertiesAbu DhabiRamhan Island
1 December 2027GEM ResidencesEagle HillsSharjahAl Khan
1 December 2027Vista Phase 3 By ReportageReportage Real EstateAbu DhabiAl Reem Island
1 December 2027Playa Del SolEllingtonRas Al KhaimahAl Marjan Island
1 December 2027Reeman ResidencesNord DevelopmentAbu DhabiAl Shamkha
1 December 2027Trio Isle CDurar GroupRas Al KhaimahAl Marjan Island
1 December 2027One CentralPantheon DevelopmentRas Al KhaimahRAK Central
1 December 2027Nouran LivingAldar PropertiesAbu DhabiSaadiyat Island
1 December 2027Opula ResidenceDHB PropertiesAbu DhabiYas Island
1 December 2027Radisson Residences Tower 2Royal Development HoldingAbu DhabiAl Reem Island
1 December 2027Aqua MayaBNW DevelopmentsRas Al KhaimahAl Marjan Island
1 December 2027AlmeriaBloom PropertiesAbu DhabiKhalifa City
1 December 2027Coral Beach VillasSobha RealtyUmm Al QuwainUmm Al Quwain Marina
1 December 2027NH CollectionRRS International DevelopmentRas Al KhaimahAl Marjan Island
1 December 2027Al Thuraya IslandAjmal MakanSharjahSharjah Waterfront City
1 December 2027The Beach Vista by RangeRange DevelopmentsRas Al KhaimahAl Marjan Island
1 December 2027Vida ResidencesAl Ain HoldingAbu DhabiSaadiyat Island
1 December 2027Selene Beach ResidencesSobha RealtyUmm Al QuwainUmm Al Quwain Marina
1 December 202788 TowerAl ThuriahSharjahAl Khan
1 December 2027Radisson ResidencesRoyal Development HoldingAbu DhabiAl Reem Island
1 December 2027Nama Phase 1 By Alef GroupAlef GroupSharjahMuwaileh
1 December 2027Vienna House Beach ResidencesSugee GroupRas Al KhaimahAl Marjan Island
1 December 2027Oasis Tower 3 by GJGJ Real EstateAjmanAl Rashidiya
1 December 2027NarenjAradaSharjahTilal City
1 December 2027Al Deem TownhomesAldar PropertiesAbu DhabiAl Bahya
1 December 2027Faya Al SaadiyatAldar PropertiesAbu DhabiSaadiyat Island
Handovers and delays in the news

Mentions in news, videos and podcasts that name a project. Follow the link for what was said.

PublishedEventProjectDeveloperDate mentionedSource
31 October 2026handed overRaana——youtube research
31 October 2026handed overMasaar 3 (first three clusters)Arada—youtube research
31 October 2026handed overMasaar 3 (last four clusters)Arada—youtube research
31 October 2026completedElemental 78——youtube research
28 October 2026completedBeach TowersAl Badie Group2013-01yt meta
28 October 2026completedAnoaOmniat—youtube research
25 October 2026handed overAl BarariZaya2003youtube research
23 October 2026handed overArbor View—2026-05yt meta
23 October 2026handed overNAS 3Rabdan2026-05yt meta
23 October 2026delayedRiviera Chalet——roundup chatter
22 October 2026handed overNoorDeyaar—famproperties
22 October 2026handed overDaniaDeyaar—famproperties
22 October 2026handed overAfnanDeyaar—famproperties
22 October 2026completed399 Hills ParkNational Properties—launch news
22 October 2026completedJumeirah Living Marina GateSelect Group2020famproperties
22 October 2026completedBinghatti AvenueBinghatti2022famproperties
22 October 2026completedBinghatti OnyxBinghatti2024famproperties
22 October 2026completedBinghatti CanalBinghatti2023famproperties
21 October 2026handed overPeninsula 5—2025hausandhaus
21 October 2026handed overHarmony—2023-12hausandhaus
18 October 2026delayedDWTN ResidencesDeyaar—youtube research
14 October 2026handed overFron's K2P villas——youtube research
9 October 2026handed overPeninsula——youtube research
15 September 2026completedHelvetia ResidencesDHG Properties—zawya
1 September 2026handed overCavalli EstatesDamac2026zawya
1 September 2026handed overUtopiaDamac2026zawya
26 August 2026handed overDanah Bay—2026-Q2zawya
26 August 2026handed overIl Teatro Residences—2026-Q2zawya
24 August 2026handed overThe Lana—2024famproperties
24 August 2026delayedHaven Living—2026-03bhomes
24 August 2026handed overHaven Living—2026-Q1bhomes
20 August 2026handed overJebel Ali VillageNakheel2026-08thenational
12 August 2026handed overEden House The Canal—2026gulfnews
3 August 2026handed overChic TowerDAMAC2026zawya
3 August 2026handed overDAMAC HillsDAMAC2026zawya
3 August 2026handed overDAMAC Hills 2DAMAC2026zawya
3 August 2026handed overDAMAC LagoonsDAMAC2026zawya
3 August 2026handed overElegance TowerDAMAC2026zawya
28 July 2026completedV1TERObject 12026zawya
24 July 2026completedJumeirah Living Business Bay—2025-12bhomes
23 July 2026completedWaha LivingAlyakka Developers—zawya
22 July 2026handed overSAMANA MiamiSAMANA Developers—zawya
22 July 2026handed overSAMANA MiamiSAMANA Developers2026-07zawya
26 June 2026handed overEquiti HomeB.N.H2025bhomes
17 June 2026handed overDanah BayDubai Investment Real Estate2026-06-17zawya
8 May 2026handed overSamana SantoriniSAMANA Developers2026-04zawya
5 May 2026handed overSerenia LivingPalma Development2026-04bhomes
5 May 2026completedSerenia LivingPalma Development2026-02bhomes
22 April 2026handed overSkyhills Residences 1HRE Development2026-04khaleejtimes
21 April 2026handed overSkyHills Residences 1HRE Development—zawya
21 April 2026handed overSkyHills Residences 1HRE2026-04-20zawya
20 April 2026handed overThe ResidencePrestige One Developments2026-04zawya
29 March 2026handed overCreek Views 2Azizi Developments—gulfnews
29 March 2026handed overCreek Views 1Azizi Developments—gulfnews
25 March 2026handed overCreek Views IIAzizi—zawya
25 March 2026handed overCreek Views IAzizi—zawya
12 February 2026handed overAltia OneYAS Developers—zawya
12 February 2026handed overAltia ResidenceYAS Developers—zawya
26 December 2025handed overFloarea ResidenceMashriq Elite2025gulfnews
3 December 2025handed overDanah Bay Phase 1—2025-Q3zawya
[1]

Still selling, barely building: the delay tracker · Supply by registered date · Snagging and handover checklist

Sources
  1. Table: Handovers and delays in the news — Sources: Dubai Land Department project register (data of 15 June 2026), DLD open-data project feed read daily since 26 October 2026, Property Finder project records (developer handover dates, locations), and BUY DUBAI's reading of news, video and podcast mentions. Homes = units + villas. Projected finish = start date + time elapsed ÷ per cent built (10–99% built only). Developer names shortened from the register. Data to 6 November 2026.