Are JVC projects finished on time
The register lists 64 JVC projects. 34 had an end date before 11 October 2026, and 7 of those are finished.
The other 27 are late by the register's own dates. They hold 6,830 homes. Their median progress is 51.5% complete. The median time past the end date is 3.4 months.
Across Dubai, the same register shows 61 of 202 due projects finished. That is 30.2%, against 20.6% in JVC. Late projects across Dubai are a median 60.1% complete.
Limits of this page.
- The register shows the end date as it stands today. It does not show the date first promised to buyers.
- Per cent complete is from the last inspection date shown. Work done after that date is not counted.
- A late date in the register does not prove a late handover to buyers. A sale contract can set a different date.
- Our copy of the register holds only projects with a start or end date in 2026. Older and later projects are not in it.
- Finished means the register status is finished, or it shows a completion date, or it shows 100% complete or more.
Source: Dubai Land Department project register, read 9 October 2026. Our copy holds only projects with a start or end date in 2026. Status is worked out for 11 October 2026. A median here is the middle value of the late projects in the row. On the sales pages a median needs 5 or more sales.
All 64 JVC projects in the register
Late projects come first, with the longest time past the end date at the top.
Then come projects not yet due, by end date. Finished projects are last. A project name opens its building page when the names match, and 50 do.
| Project | Developer | Homes | Register end date | Per cent complete | Date inspected | Status on 11 October 2026 |
|---|---|---|---|---|---|---|
| Binghatti Amberhall | Binghatti | 1,157 | 28 February 2026 | 38 | 12 January 2026 | Late by 7.4 months |
| Binghatti Ruby | Binghatti | 628 | 28 February 2026 | 46.4 | 20 July 2026 | Late by 7.4 months |
| Lodge Residences by Riviera Azure | Riviera Azure | 56 | 1 March 2026 | 63.3 | 13 July 2026 | Late by 7.4 months |
| Samana Waves 2 | Samana | 173 | 20 March 2026 | 52.1 | 24 September 2026 | Late by 6.7 months |
| Palatium Residences | Ahmadyar | 151 | 31 March 2026 | 87.9 | 14 September 2026 | Late by 6.4 months |
| Roma Residences by JRP | JRP | 80 | 31 March 2026 | 76.8 | 15 September 2026 | Late by 6.4 months |
| Almaan 101 | MN Vision | 102 | 13 April 2026 | 50.9 | 11 March 2026 | Late by 5.9 months |
| Elysee Heights | Pantheon | 193 | 14 April 2026 | 81.2 | 18 May 2026 | Late by 5.9 months |
| Samana Waves | Samana | 217 | 15 April 2026 | 90.1 | 13 May 2026 | Late by 5.9 months |
| Parkwood Residences | Arabian Gulf | 174 | 30 April 2026 | 57 | 14 September 2026 | Late by 5.4 months |
| Waref Residences by Sido Development | Sido | 228 | 1 May 2026 | 81.1 | 8 April 2026 | Late by 5.4 months |
| Skyhills II by HRE | HRE | 560 | 1 June 2026 | 95 | 20 July 2026 | Late by 4.3 months |
| Casa Vista Residence by Golden Woods | Casa Vista & Golden Woods | 90 | 30 June 2026 | 90 | 3 June 2026 | Late by 3.4 months |
| Lucky Oasis Residence | Lucky Aeon | 144 | 30 June 2026 | 20 | 30 April 2026 | Late by 3.4 months |
| Violet Tower | Dubai Investment Real Estate | 289 | 30 June 2026 | 70.4 | 3 June 2026 | Late by 3.4 months |
| The Fifth Tower | Object One | 345 | 24 July 2026 | 50.3 | 22 July 2026 | Late by 2.6 months |
| Aveline Residences by Citi Developers | Citi | 568 | 26 July 2026 | 42.2 | 11 June 2026 | Late by 2.5 months |
| The Orchard Place | Peak Summit | 418 | 31 July 2026 | 42.7 | 31 March 2026 | Late by 2.4 months |
| Rose Gardens 2 | Cavara | 71 | 30 August 2026 | 31.8 | 2 June 2026 | Late by 1.4 months |
| Belle Reve by Zimaya | Zimaya | 360 | 31 August 2026 | 80.5 | 7 September 2026 | Late by 1.3 months |
| Sereno Residences | Svarn | 94 | 1 September 2026 | 22.4 | 29 July 2026 | Late by 1.3 months |
| 77 Boulevard by Bam | Bam | 58 | 10 September 2026 | 18 | 16 March 2026 | Late by 1.0 months |
| Havelock Heights | AA and HMB | 156 | 15 September 2026 | 28 | 17 June 2026 | Late by 0.9 months |
| Exotica by Al Marina | Al Marina Investment | 93 | 30 September 2026 | 41.1 | 15 May 2026 | Late by 0.4 months |
| Eco Harmony Tower | Green Point Home | 107 | 1 October 2026 | – | – | Late by 0.3 months |
| Hearth Heights by ENAWT Real Estate Development | Enawt | 142 | 1 October 2026 | 29.1 | 24 June 2026 | Late by 0.3 months |
| Vue by Crystal Bay | Crystal Bay | 176 | 1 October 2026 | 68.2 | 20 August 2026 | Late by 0.3 months |
| Golden Wood Views 5 | Golden Wood | 161 | 14 October 2026 | 89 | 30 March 2026 | Not yet due |
| Samha Residence 2 | Samha | 175 | 15 October 2026 | 52.1 | 10 August 2026 | Not yet due |
| Pure Town | Livex | – | 22 October 2026 | 0 | 19 June 2025 | Not yet due |
| Orchid Residence | West F5 | – | 30 October 2026 | – | – | Not yet due |
| Manhattan 2 by SD | Samana | 193 | 1 November 2026 | 21.2 | 10 September 2026 | Not yet due |
| Luxur Tower by Imtiaz | Imtiaz | 361 | 15 December 2026 | 90 | 14 September 2026 | Not yet due |
| Sapphire 32 by Dar Alkarama | Dar Al Karama | 232 | 15 December 2026 | 62.3 | 29 June 2026 | Not yet due |
| Zenith Tower J1 | Zenith Ventures | 76 | 25 December 2026 | 72.2 | 25 July 2026 | Not yet due |
| 18 Marlow Row | Sai Avani | – | 31 December 2026 | 51.9 | 2 September 2026 | Not yet due |
| Hillmont Residences by Ellington | BLG | 145 | 31 December 2026 | 26.3 | 13 July 2026 | Not yet due |
| Livel Residenza | Vantage Capital | 137 | 31 December 2026 | 20 | 24 June 2026 | Not yet due |
| Vita Grande by Meteora | Meteora | 121 | 31 December 2026 | 63.8 | 22 January 2026 | Not yet due |
| 1wood Residence 2 | Object One | 209 | 20 October 2027 | 0 | 27 February 2026 | Not yet due |
| Binghatti Etherea | Binghatti | 287 | 31 December 2027 | 7.2 | 9 September 2026 | Not yet due |
| Tresora by Wadan | Wadan | 160 | 30 March 2028 | 0 | 9 March 2026 | Not yet due |
| Sol Terra Casa I | SOL | – | 15 June 2028 | 0 | 27 February 2026 | Not yet due |
| Sol Terra Casa II | SOL | – | 15 June 2028 | 0 | 14 April 2026 | Not yet due |
| Shape | Redix One | – | 30 June 2028 | 0 | 23 February 2026 | Not yet due |
| 368 Park Ln | Tabeer | 213 | 31 August 2028 | 0 | 4 November 2025 | Not yet due |
| The Weave | The Weave | 130 | 1 September 2028 | 7.6 | 13 July 2026 | Not yet due |
| Beverly Crown | HMB Homes | 214 | 31 December 2028 | 0 | 23 June 2026 | Not yet due |
| S'VN Residences | Metrical | 201 | 31 December 2028 | 0 | 16 June 2026 | Not yet due |
| Sky Harmony by Peace Homes | Peace Homes | 197 | 20 January 2029 | 12.6 | 2 September 2026 | Not yet due |
| The Hudson | Crystal Prime | 96 | 14 February 2029 | 0 | 16 January 2026 | Not yet due |
| Sky Level 1 | Object One | 440 | 28 February 2029 | 0 | 12 May 2026 | Not yet due |
| Oxford Cove | Iman | 465 | 30 March 2029 | 0 | 4 February 2026 | Not yet due |
| Aura Heights | Serenity Century | 150 | 1 April 2029 | 0 | 29 July 2026 | Not yet due |
| Coventry Living | GFS Wonders | 200 | 1 July 2029 | 0 | 5 May 2026 | Not yet due |
| Laya Crest | Laya | – | 1 October 2029 | – | – | Not yet due |
| Serenz by Danube | Danube | 1,227 | 31 December 2029 | 0.1 | 10 July 2026 | Not yet due |
| Binghatti Grove | Binghatti | 1,065 | 31 March 2026 | 100 | 24 September 2026 | Finished |
| Park Lane 2 by Heilbronn | Heilbronn | 183 | 31 March 2026 | 100 | 27 January 2026 | Finished |
| The Veranda Collection 2 | Pacifique Global | – | 7 April 2026 | 100 | 24 July 2026 | Finished |
| Binghatti Apex | Binghatti | 1,230 | 30 April 2026 | 100 | 8 April 2026 | Finished |
| Terrazzo Residences | Taraf | 211 | 20 May 2026 | 100 | 6 July 2026 | Finished |
| Skyhills III by HRE | HRE | 563 | 1 June 2026 | 100 | 27 August 2026 | Finished |
| Pearl House III by Imtiaz | Imtiaz | 356 | 1 August 2026 | 100 | 20 April 2026 | Finished |
A dash for homes means the register shows none yet. "Late by" counts months from the register end date to 11 October 2026.
Source: Dubai Land Department project register, read 9 October 2026. Our copy holds only projects with a start or end date in 2026. Status is worked out for 11 October 2026. A median here is the middle value of the late projects in the row. On the sales pages a median needs 5 or more sales. A project is matched to a building by name.
JVC projects by developer
29 developers had a JVC project with an end date before 11 October 2026.
Every figure is what the register showed on 9 October 2026. Companies of one developer are joined under one name.
| Developer | Projects | Homes | Due before 11 October 2026 | Finished | Late | Homes in late projects | Median per cent complete, late | Median months late |
|---|---|---|---|---|---|---|---|---|
| Binghatti | 5 | 4,367 | 4 | 2 | 2 | 1,785 | 42.2 | 7.4 |
| HRE | 2 | 1,123 | 2 | 1 | 1 | 560 | 95.0 | 4.3 |
| Samana | 3 | 583 | 2 | 0 | 2 | 390 | 71.1 | 6.3 |
| Object One | 3 | 994 | 1 | 0 | 1 | 345 | 50.3 | 2.6 |
| Imtiaz | 2 | 717 | 1 | 1 | 0 | 0 | – | – |
| Citi | 1 | 568 | 1 | 0 | 1 | 568 | 42.2 | 2.5 |
| Peak Summit | 1 | 418 | 1 | 0 | 1 | 418 | 42.7 | 2.4 |
| Zimaya | 1 | 360 | 1 | 0 | 1 | 360 | 80.5 | 1.3 |
| Dubai Investment Real Estate | 1 | 289 | 1 | 0 | 1 | 289 | 70.4 | 3.4 |
| Sido | 1 | 228 | 1 | 0 | 1 | 228 | 81.1 | 5.4 |
| Taraf | 1 | 211 | 1 | 1 | 0 | 0 | – | – |
| Pantheon | 1 | 193 | 1 | 0 | 1 | 193 | 81.2 | 5.9 |
| Heilbronn | 1 | 183 | 1 | 1 | 0 | 0 | – | – |
| Crystal Bay | 1 | 176 | 1 | 0 | 1 | 176 | 68.2 | 0.3 |
| Arabian Gulf | 1 | 174 | 1 | 0 | 1 | 174 | 57.0 | 5.4 |
| AA and HMB | 1 | 156 | 1 | 0 | 1 | 156 | 28.0 | 0.9 |
| Ahmadyar | 1 | 151 | 1 | 0 | 1 | 151 | 87.9 | 6.4 |
| Lucky Aeon | 1 | 144 | 1 | 0 | 1 | 144 | 20.0 | 3.4 |
| Enawt | 1 | 142 | 1 | 0 | 1 | 142 | 29.1 | 0.3 |
| Green Point Home | 1 | 107 | 1 | 0 | 1 | 107 | – | 0.3 |
| MN Vision | 1 | 102 | 1 | 0 | 1 | 102 | 50.9 | 5.9 |
| Svarn | 1 | 94 | 1 | 0 | 1 | 94 | 22.4 | 1.3 |
| Al Marina Investment | 1 | 93 | 1 | 0 | 1 | 93 | 41.1 | 0.4 |
| Casa Vista & Golden Woods | 1 | 90 | 1 | 0 | 1 | 90 | 90.0 | 3.4 |
| JRP | 1 | 80 | 1 | 0 | 1 | 80 | 76.8 | 6.4 |
| Cavara | 1 | 71 | 1 | 0 | 1 | 71 | 31.8 | 1.4 |
| Bam | 1 | 58 | 1 | 0 | 1 | 58 | 18.0 | 1.0 |
| Riviera Azure | 1 | 56 | 1 | 0 | 1 | 56 | 63.3 | 7.4 |
| Pacifique Global | 1 | 0 | 1 | 1 | 0 | 0 | – | – |
See JVC developers for the buildings and sales of each developer.
Source: Dubai Land Department project register, read 9 October 2026. Our copy holds only projects with a start or end date in 2026. Status is worked out for 11 October 2026. A median here is the middle value of the late projects in the row. On the sales pages a median needs 5 or more sales.
JVC projects by size
Projects of 500 homes or more finished 3 of 7 that were due. Smaller projects finished 4 of 27.
| Project size | Projects | Homes | Due before 11 October 2026 | Finished | Late | Homes in late projects | Median per cent complete, late | Median months late |
|---|---|---|---|---|---|---|---|---|
| Under 100 homes | 17 | 714 | 8 | 1 | 7 | 542 | 41.1 | 1.4 |
| 100 to 249 homes | 30 | 5,195 | 14 | 2 | 12 | 1,963 | 57.0 | 5.4 |
| 250 to 499 homes | 9 | 3,321 | 5 | 1 | 4 | 1,412 | 60.4 | 2.5 |
| 500 homes or more | 8 | 6,998 | 7 | 3 | 4 | 2,913 | 44.3 | 5.8 |
Source: Dubai Land Department project register, read 9 October 2026. Our copy holds only projects with a start or end date in 2026. Status is worked out for 11 October 2026. A median here is the middle value of the late projects in the row. On the sales pages a median needs 5 or more sales.
JVC against Dubai and nearby areas
JVC finished 20.6% of its due projects. All of Dubai finished 30.2%.
| Area | Projects | Homes | Due before 11 October 2026 | Finished | Finished, per cent | Late | Homes in late projects | Median per cent complete, late | Median months late |
|---|---|---|---|---|---|---|---|---|---|
| JVC | 64 | 16,228 | 34 | 7 | 20.6% | 27 | 6,830 | 51.5 | 3.4 |
| Dubai, all areas | 709 | 221,039 | 202 | 61 | 30.2% | 141 | 32,070 | 60.1 | 3.4 |
| Dubai without JVC | 645 | 204,811 | 168 | 54 | 32.1% | 114 | 25,240 | 63 | 3.7 |
| Jumeirah Village Triangle | 19 | 3,980 | 7 | 4 | 57.1% | 3 | 459 | 76.1 | 6.4 |
| Arjan | 15 | 5,658 | 6 | 2 | 33.3% | 4 | 1,498 | 73.5 | 5.3 |
| Dubai Sports City | 8 | 3,321 | 8 | 4 | 50% | 4 | 2,064 | 68.2 | 6.4 |
| Dubai South | 75 | 14,812 | 12 | 2 | 16.7% | 10 | 773 | 66 | 2.5 |
| Business Bay | 26 | 23,160 | 11 | 4 | 36.4% | 7 | 2,885 | 52 | 4.4 |
JVC projects by the year of the register end date
| End year | Projects | Homes | Finished | Median per cent complete |
|---|---|---|---|---|
| 2026 | 46 | 12,039 | 7 | 62.8 |
| 2027 | 2 | 496 | 0 | 3.6 |
| 2028 | 8 | 918 | 0 | 0 |
| 2029 | 8 | 2,775 | 0 | 0 |
No comparison with a year before is possible from this file.
Source: Dubai Land Department project register, read 9 October 2026. Our copy holds only projects with a start or end date in 2026. Status is worked out for 11 October 2026. A median here is the middle value of the late projects in the row. On the sales pages a median needs 5 or more sales.
Common questions
How many JVC off-plan projects are late?
The Dubai Land Department project register was read on 9 October 2026. It lists 64 JVC projects. 34 had an end date before 11 October 2026 and 7 of those are finished. The other 27 are late by the register's dates.
Which JVC projects are furthest past their register end date?
The register shows these three unfinished projects with the earliest end dates. Binghatti Amberhall: end date 28 February 2026, 38% complete at the inspection of 12 January 2026. Binghatti Ruby: end date 28 February 2026, 46.4% complete at the inspection of 20 July 2026. Lodge Residences by Riviera Azure: end date 1 March 2026, 63.3% complete at the inspection of 13 July 2026.
Which late JVC projects show the least progress?
These three late projects show the lowest per cent complete at the last inspection. 77 Boulevard by Bam: 18% on 16 March 2026, with an end date of 10 September 2026. Lucky Oasis Residence: 20% on 30 April 2026, with an end date of 30 June 2026. Sereno Residences: 22.4% on 29 July 2026, with an end date of 1 September 2026.
How many homes are in late JVC projects?
The 27 late projects hold 6,830 homes. All 64 JVC projects in the register hold 16,228 homes.
Does a late date in the register mean my handover is late?
No. The register shows the end date as it stands today, not the date first promised. Per cent complete is from the last inspection shown. Your sale contract sets your own handover date.
How does JVC compare with the rest of Dubai?
JVC finished 7 of 34 due projects, or 20.6%. Across Dubai the register shows 61 of 202 finished, or 30.2%. Late JVC projects are a median 51.5% complete, against 60.1% across Dubai.
How is "late" worked out on this page?
A project is late when its register end date is before 11 October 2026 and it is not finished. Finished means the register status is finished, or it shows a completion date, or it shows 100% complete or more.
Source: Dubai Land Department project register, read 9 October 2026. Our copy holds only projects with a start or end date in 2026. Status is worked out for 11 October 2026. A median here is the middle value of the late projects in the row. On the sales pages a median needs 5 or more sales.